Standard Guide for Painting Inspectors (Metal Substrates)
1.1 This guide is intended as an information aid to painting inspectors in carrying out their task efficiently. It includes the key elements of the inspection of surface preparation, coatings application, and final approval for both field and shop work. The items should be selected that are pertinent to the specification of a particular job.
Note 1: For additional helpful information, refer to the following documents:
1.2 Certain industries or owners may require certified inspection personnel. See Guide D4537 for establishing procedures to certify inspectors for coatings work in nuclear power generating facilities.
1.3 The values stated in SI units are to be regarded as the standard. The values given in parentheses are for information only.
1.4 This guide is arranged in the following order:
| Referenced Documents | 2 |
| ASTM Standards | 2.1 |
| OSHA Standards | 2.2 |
| Steel Structures Painting Council Publications | 2.3 |
| International Standards Organization (ISO) | 2.4 |
| ASTM Adjuncts | 2.6 |
| Significance and Use | 3 |
| Preparation for Inspection | 4 |
| Surface Preparation Methods and Requirements | 5 |
| Surface Preparation | 5.1 |
| Pictorial Standard D2200 | 5.1.1 |
| Factors Affecting Coating Performance | 5.2 |
| Cleanliness | 5.2.1 |
| Mill Scale | 5.2.2 |
| Surface Profile | 5.2.3 |
| Sharp Edges | 5.2.4 |
| Cleaning Procedures | 5.3 |
| Chemical Cleaning | 5.3.1 |
| Solvent Vapor Cleaning | 5.3.1.1 |
| Hand Tool Cleaning | 5.3.2 |
| Power Tool Cleaning | 5.3.3 |
| Power Tool Cleaning to Bare Metal | 5.3.4 |
| Commercial Grade Power Tool Cleaning | 5.3.4.4 |
| Blast Cleaning | 5.3.5 |
| Pressurized Water Cleaning | 5.3.6 |
| Cleaning and Preparation of Various Surfaces | 5.4 |
| Steel Surfaces | 5.4.1 |
| Galvanized Surfaces | 5.4.2 |
| Aluminum Surfaces | 5.4.3 |
| Precautions in Preparing Unpainted and Previously | |
| Painted Surfaces | 5.4.4 |
| Inspection of Surfaces Prior to Field Painting | 5.5 |
| New Construction | 5.5.1 |
| Maintenance Repainting | 5.5.2 |
| Coating Storage and Handling | 6 |
| Storage of Coating and Thinner | 6.1 |
| Mixing of Coatings | 6.2 |
| Thinning | 6.3 |
| Thinning of Coating | 6.3.1 |
| Sampling of Thinned Coating | 6.3.2 |
| Heating of Coating | 6.4 |
| Weather Considerations | 7 |
| Drying | 7.1 |
| Low Temperature | 7.2 |
| High Temperature | 7.3 |
| Moisture | 7.4 |
| Wind | 7.5 |
| Coating Application | 8 |
| Residual Contaminants | 8.1 |
| Quality Assurance | 8.2 |
| Film Defects | 8.2.1 |
| Brush Application | 8.3 |
| Spray Application | 8.4 |
| Roller Application | 8.5 |
| Miscellaneous Methods | 8.6 |
| Rate of Application | 8.7 |
| Additional Considerations | 9 |
| Ventilation | 9.1 |
| Shopcoat Repair | 9.2 |
| Painting Schedule | 9.3 |
| Film Integrity | 9.4 |
3.1 This guide is intended as a reference for those concerned with the inspection of industrial coating work.
The requirements for inspection should be addressed in all protective coating and lining work specifications.
This guide may be used by specification writers when selecting and establishing the inspection requirements for coating and lining specifications.
A checklist for use by inspectors in the field is included in Appendix X1.